  • Another Record Amount of Roadwork Underway in Broome

    For the second straight summer, Broome County will be conducting a record amount of roadwork. County Executive Jason Garnar joined Deputy Commissioner of Public Works Sue Brown on site of the latest project to highlight the work.

                “Repairing and replacing our infrastructure is always one of the biggest issues for our residents,” Garnar said. “Now, we’re investing in our roads and bridges like never before; we did a record number of miles of road last year and we’re topping it this year. Some of these roads haven’t been touched in years and our DPW crews are doing a great job to make the drive better for all travelers.”

                The 2022 highway reconstruction and rehabilitation plan includes more than 20 projects. Nearly 30 miles of roads will be milled and paved, while another 44 miles are scheduled to be sealed; a record total of more than 72 miles of roadways; a complete list of anticipated road projects can be found below. Weekly roadwork updates will be provided to help drivers plan their commute.

                Motorists are reminded to use caution in work zones, even when they are not active as some routes may be modified as construction progresses. Slowing down is always the most effective way to keep yourself and workers safe. You may also want to give yourself extra time during commutes to accommodate for any detours or changes in traffic patterns.

    2022 Anticipated Road Projects

    (subject to change)

     

      2022 HIGHWAY CONSTRUCTION/REHAB  PROJECTS    
    ROAD MILES  DESCRIPTION   
    EAST WINDSOR ROAD  (No. 1148 to  County Line) 4.55 3/4″ OVERLAY  COLESVILLE 
    TRIM STREET (Village Line to Dickinson Road)) 4.01 3/4″ OVERLAY  KIRKWOOD 
    OLD ROUTE 17 (Damascus to NYS Rte 41) 8.5 1.125″  MILL & FILL  SANFORD 
    CALDWELL HILL ROAD (Arnold Road to Town Line) 2.0 2″ BINDER  LISLE 
    OUAQUAGA ROAD  2.09 COLD MIX PAVE  COLESVILLE 
    OUAQUAGA ROAD  2.09 IN-PLACE REYCLE  COLESVILLE 
    MAIN STREET 2.0  1.125″ MILL & FILL   KIRKWOOD 
    BRIDGE STREET 0.3  1.125″ MILL & FILL   KIRKWOOD 
    ROUTE 11 RAMPS 0.44 1.125″ MILL & FILL  KIRKWOOD 
    OQUAGA LAKE ROAD (Hanson Road to Golf Course) 2.6 3/4″ OVERLAY  SANFORD 
           
    TOTAL 28.58    
           
    CHIP SEAL      
    BALLYHACK ROAD 4.36 CHIP SEAL   FENTON 
    GANOUNGTOWN ROAD 1.64 CHIP SEAL   FENTON 
    CONKLIN FORKS ROAD (Murphy Road to Brady Hill Road) 1.3 CHIP SEAL   CONKLIN 
    NORTH SANFORD ROAD 8.22 CHIP SEAL   SANFORD 
    NOWLAN  ROAD (D&H RR to Stratmill Road) 2.49 CHIP SEAL   FENTON 
    SADDLEMIRE ROAD 3.35 CHIP SEAL   BINGHAMTON 
    TUNNEL ROAD 4.85 CHIP SEAL   COLESVILLE/FENTON 
     AIRPORT ROAD (Chenango Bridge) 1.71 CHIP SEAL   CHENANGO 
    BROOKS ROAD 3.02 CHIP SEAL   CHENANGO 
    CALDWELL HILL ROAD(HM Baldwin NYS Rte 79) 2.39 CHIP SEAL   LISLE 
    FARM TO MARKET ROAD (Twist Run Road to East Maine Road) 3.63 CHIP SEAL   UNION 
    GREENWOOD ROAD 1.75 CHIP SEAL   NANTICOKE 
    HUNTS CORNERS ROAD 0.94 CHIP SEAL   LISLE 
    NORTH STREET 4.4 CHIP SEAL  TRIANGLE
           
           
           
    TOTAL 44.05    
    TOTAL MILEAGE 72.63    
  • Road Closure Notice in Village of Deposit

    (VILLAGE OF DEPOSIT, NY) From the Broome County Department of Public Works: A drainage improvement project will be taking place on Second Street (CR – 315) in the Village of Deposit between Church and Dean Streets.  The highway closure is scheduled to begin at 7:00 am on May 25, 2022 and will re‐open to traffic on or about 5:00 pm on or before July 1, 2022.   

     Residents within this block will be granted access to their homes, however through traffic will need to seek alternate routes while the road is closed.  A signed detour will remain in place through the closure end date.

    If you have any questions or concerns regarding this scheduled road closure, please feel free to contact the Broome County Project Manager, Brenda Gowe at 607‐778‐2470 or by email at Brenda.Gowe@broomecounty.us.  

  • Road Closure Notice

    Page Brook & Greenwood Rds. to be Closed

    From the Broome County Department of Public Works: Page Brook Road, a County-owned road in the Town of Triangle, will be closed to traffic on September 30, 2021 at 7:00 AM and will reopen to traffic on or about 4:00 PM October 4, 2021. The road will be closed from the intersection of NY Rt. 26 to English Hill Rd. for culvert replacement.

    Additionally, Greenwood Road, a County-owned road in the Town of Nanticoke, will be closed to traffic on October 4, 2021 at 7:00 AM and will reopen to traffic on or about 4:00 PM October 7, 2021. The road will be closed from the intersections of Quinleven Rd. to Caldwell Hill Rd. for culvert replacement.

    All local traffic will need to seek alternate routes while the roads are closed. Signed detour routes will be posted.

  • Airport Road to be Closed for Culvert Replacement

    From the Broome County Department of Public Works: A portion of Airport Road, a County-owned road in the Town of Maine, will be closed to traffic on September 13, 2021 at 7:00 AM and reopen to traffic on or about 4:00 PM September 22, 2021. The road will be closed from the intersection of Commercial Drive to Arbutus Road for culvert replacement.

    All local traffic will need to seek alternate routes while the road is closed. A signed detour route will be posted utilizing Commercial Drive, East Maine Road, and Arbutus Road. Additional information may be obtained by contacting Martin Haley, Engineer I at (607) 778-2463 or emailing him at Martin.Haley@BroomeCounty.us.

  • Road Closure Notice: Old Rt. 17

    Old Route 17 to be Closed for Culvert Construction

    (TOWN OF WINDSOR, NY) From the Broome County Department of Public Works: Old Route 17 (CR 28), a County-owned highway located in the Town of Windsor, shall be closed to traffic on September 7, 2021 at 7:00 am and reopened to traffic on or about 5:00 pm November 9, 2021. The closure shall be in the vicinity of the Old Route 17 and Ostrander Road intersection. The road will be closed for the purpose of concrete box culvert construction.

    All local traffic will need to seek alternate routes while the road is closed. A signed detour route will be posted. A detour map can be found here.

    If you have questions, please contact Tom Sullivan at (607) 778-2496 or Thomas.Sullivan@BroomeCounty.us.

  • Broome County Highway Work Planned for Week of 8/30

    Broome County Executive Jason Garnar and Sue Brown, Highway Commissioner, released the following highway work planned for the week beginning August 30th:

    • Patching on Caldwell Hill and Nanticoke Roads
    • Storm and flash flood cleanup will continue along the County roadway system
    • Ditching will be performed on Hawleyton & Powderhouse Roads and Old Route 17 
    • Brush & tree cutting will continue
    • The Highway Division will be replacing pipes along roadway system
    • Guiderail repairs along County roadway system
    • Striping County and Town roadways
    • Mowing the right of way along County Roadway system
  • Broome County Highway Work Planned for Week of 8/23

    Broome County Executive Jason Garnar and Sue Brown, Highway Commissioner, released the following highway work planned for the week beginning August 23rd:

    • Paving continues on Smith Hill and Lewis Roads
    • The Highway Division will continue patching on Caldwell Hill Road.
    • Storm and flash flood cleanup will continue along the County roadway system after another round of storms on 8/22/2021
    • Ditching will be performed on Hyde Street, Center Village Loop, and Ouaquaga Roads, and Old Route 17
    • Brush & tree cutting will continue.
    • Pipe replacement along roadway system
    • Guiderail repairs along County roadway system
    • Striping along County and Town roadways
    • Mowing right of way along County roadway system
  • Broome County Highway Work Planned for Week of 8/16

    Broome County Executive Jason Garnar and Sue Brown, Highway Commissioner, released the following highway work planned for the week beginning August 16th:

    • Paving on Smith Hill and Lewis Roads
    • Patching on Caldwell Hill Road
    • Storm & flash flood cleanup will continue along the County roadway system
    • Ditching will be performed on Hawleyton, Powderhouse, Colesville, Center Village Loop and Ouaquaga Roads, and Park Avenue 
    • Brush & tree cutting will continue.
    • Pipe replacement on Brady Hill and Kattelville Roads and Trim Street
    • Guiderail repairs along County roadway system
    • Striping on various County and Town roadways
    • Mowing right of way along County roadway system
  • Broome County Highway Work Planned for Week of 8/9

    (BINGHAMTON, NY) Broome County Executive Jason Garnar and Sue Brown, Highway Commissioner, released the following highway work planned for the week beginning August 9th:

    • Milling on Smith Hill and Lewis Roads to be followed by paving
    • Patch work on Pagebrook and Upper Lisle  Roads
    • Storm and flash flood cleanup will continue along the County roadway system
    • Ditching will be performed on Glenwood, Owen Hill, and Knapp Hill Roads 
    • Brush and tree cutting will continue
    • Guiderail repairs will be conducted along County roadway system
    • Striping of County and Town roadways with paint truck
    • Mowing along the right of way along County roadway system
  • Broome County Highway Work Planned for Week of 8/2

    Broome County Executive Jason Garnar and Sue Brown, Highway Commissioner, released the following highway work planned for the week beginning August 2nd:

    • Flood repairs will continue on multiple County roads; opening plugged pipes, ditches, and repairing washed out shoulders
    • Patching will take place on Pagebrook Rd.
    • Culvert pipes will be replaced onare replacing culvert pipes on Kattelville and West Chenango Roads.
    • Tree cleanup from storm damage will continue
    • Guiderail repair on Cherry Valley Rd.
    • Painting will continue on County roadways